§ 8532 Stop Payment Notice Bond

Civil Code·California
AI Summary·Official Text·Key Terms·Related Statutes·References
AI SummaryVerified

§ 8532 Stop Payment Notice Bond

Key Takeaways

  • •If you're owed money for construction work, you can tell the lender to stop paying the person who hired you.
  • •You must give the lender a bond (like a promise to pay) worth 125% of what you're owed.
  • •If the court says you were wrong, you have to pay for any problems your stop payment caused, up to the bond amount.

Example

You built a garage for someone, but they didn't pay you the $10,000 they owe. The bank is lending them money for the project.

You can tell the bank to stop giving them money, but you must also give the bank a bond worth $12,500 (125% of $10,000). If the court later says you weren't owed the money, you'll have to pay for any trouble your stop payment caused, up to $12,500.

AI-generated — May contain errors. Not legal advice. Always verify source.

Official Source
View on CA.gov

§ 8532 Stop Payment Notice Bond

A claimant may give a construction lender a stop payment notice accompanied by a bond in an amount equal to 125 percent of the amount of the claim. The bond shall be conditioned that if the defendant recovers judgment in an action to enforce payment of the claim stated in the stop payment notice or to enforce a claim of lien recorded by the claimant, the claimant will pay all costs that are awarded the owner, direct contractor, or construction lender, and all damages to the owner, direct contractor, or construction lender that result from the stop payment notice or recordation of the claim of lien, not exceeding the amount of the bond. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)

Last verified: January 21, 2026

Key Terms

stop payment noticebond125 percentclaimantconstruction lender

Related Statutes

  • § 8538 Claimant Notice Of Election
  • § 8530 Lienholder Stop Payment Notice
  • § 8536 Construction Lender Payment Withholding
  • § 8502 Stop Payment Notice Requirements
  • § 8506 Stop Payment Notice Requirements

References

  • Official text at leginfo.legislature.ca.gov
  • California Legislature. Civil Code. Section 8532.
View Official Source