§ 7109 Construction Standards Violations

Business and Professions Code·California
AI Summary·Official Text·Key Terms·Related Statutes·References
AI SummaryVerified

§ 7109 Construction Standards Violations

Key Takeaways

  • •If a builder doesn't follow the usual good building rules on purpose, they can get in trouble, unless they followed special plans made by an architect.
  • •If a builder ignores the plans or rules for a building project on purpose and it hurts someone else, they can get in trouble if they didn't get permission from the owner or the person who wanted the project done right.
  • •The builder can only change the plans if the owner or the person in charge says it's okay.

Example

A builder is hired to build a house. The plans say to use strong wood for the floors, but the builder uses cheap, weak wood instead to save money.

The builder didn't follow the good building rules or the plans, and this could cause problems for the family living in the house. The builder can get in trouble for this because they didn't get permission to change the plans.

AI-generated — May contain errors. Not legal advice. Always verify source.

Official Source
View on CA.gov

§ 7109 Construction Standards Violations

(a) A willful departure in any material respect from accepted trade standards for good and workmanlike construction constitutes a cause for disciplinary action, unless the departure was in accordance with plans and specifications prepared by or under the direct supervision of an architect. (b) A willful departure from or disregard of plans or specifications in any material respect, which is prejudicial to another, without the consent of the owner or his or her duly authorized representative and without the consent of the person entitled to have the particular construction project or operation completed in accordance with such plans or specifications, constitutes a cause for disciplinary action. (Amended by Stats. 1988, Ch. 1619, Sec. 4. Effective September 30, 1988.)

Last verified: January 23, 2026

Key Terms

contractconstructionaccordanceeffective septemberoperation

Related Statutes

  • § 7107 Contractor Project Abandonment Discipline
  • § 7111 Contractor Recordkeeping Requirements
  • § 7113 Contract Price Completion Failure
  • § 7099.5 Citation Contest Hearings
  • § 7108.5 Subcontractor Progress Payment Rules

References

  • Official text at leginfo.legislature.ca.gov
  • California Legislature. Business and Professions Code. Section 7109.
View Official Source